Bill No.: SF0069 Drafter: MQ
LSO No.: 13LSO-0334 Effective Date: 7/1/2013
Enrolled Act No.: SEA0069
Chapter No.: CH0141
Prime Sponsor: Select Water Committee
Catch Title: Omnibus water bill-construction.
Subject: Provides authorization and funding for water development projects approved for final construction.
Summary/Major Elements:
2013 New Development Projects
Buffalo South Loop Pipeline
Burns Well Connection
Casper Raw Water Supply II
Cottonwood Lake Enlargement
Evansville Emergency Connection
Jeffrey City Water System Improvements
Lance Creek Well Connection
Mountain View Acres Connection
Pavillion Water System Improvements
Sheridan North Loop Transmission Line
Rehabilitation Construction Projects
Austin-Wall Canal Rehabilitation-Phase I
Cody Canal Rehabilitation 2013
Eden Valley Farson Lateral Rehabilitation – Phase I
Goshen Irrigation District Rehabilitation 2013
Midvale Rehabilitation 2013
Riverton Valley Rehabilitation 2013
Savery Creek Diversions Phase II
Shoshone Irrigation District Rehabilitation 2013
Amendments to Prior Projects
Cowley Transmission Pipeline
Eden Valley Rehabilitation 2009
Cheyenne Southern Pipeline
Buffalo Northwest Pipeline
Fort Laramie Storage Tank
Gillette Regional Extensions
Lovell Transmission Pipeline
Northwest Rural Northern Expansion
Lovell Canal Rehabilitation 2012
Comments:
See also the companion water bill, HB 71, Omnibus water bill-planning.